Question for anyone with knowledge about average cost for digging a well for house water and also a septic system.

 

Assume property not in the watershed area, most likely going to be in Chenango or Broome county.

 

I was looking at buying land and then having a double wide put on the property as a home.  Obviously the additional costs of having a well dug and a septic system or cesspool are added.

 

Any ideas???

 

 

Thanks in advance. 

 

 

Link to comment
Share on other sites

I just had a well and septic done.  My well cost a lot- over $10k.  They had to go about 260 feet down.  The price included everything- the well, the pressure tank, the pump, all the necessary wiring, etc.  The septic was about $4k.  This was in Otsego County.

Link to comment
Share on other sites

7 years ago I paid $3500 for a 180' well in Steuben county. That included everything, just turn on the water. Septic ran about $6,500. Tank and leach field. Remember you need an engineer to design the septic system. That was my case 7 years ago. Best two investments I ever made!! GL

Link to comment
Share on other sites

 

 

Wow.  That's a big price difference.  I don't know much about it- maybe the price has a bit to do with the specific area as well as the depth.  I got a couple of estimates and they were all pretty similar.  Unless maybe the cost of materials has gone up a lot over the last couple of years.

Link to comment
Share on other sites

Wow.  That's a big price difference.  I don't know much about it- maybe the price has a bit to do with the specific area as well as the depth.  I got a couple of estimates and they were all pretty similar.  Unless maybe the cost of materials has gone up a lot over the last couple of years.

soil conditions.

Link to comment
Share on other sites

Going about 5 years back...

 

Water - just under $10k. Well was 398 ft deep if I remember correctly. That included everything - pump, pressure tank, etc. All I had to do was turn on the faucet. Well pricing is generally a set fee up to xx ft and then you pay by the foot after that.

 

 

Septic - 4 BR house with 1250 gal tank. This is IN the watershed, which added to the cost - around $13k complete. Perc test will determine type of system needed. If my per rate was bad, I could have been forced to go with a system that costs twice as much. Depending on the area you are looking in, it MAY make sense to have a perc test done (based on location you plan to build) prior to closing.

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

 Share

  • Recently Browsing   0 members

    No registered users viewing this page.

×
×
  • Create New...